October 11, 2024
Rupert Resources Ltd (“Rupert” or the “Company”) announces that it has published its unaudited financial results for the three and six months ending August 31, 2024 and accompanying Management’s Discussion and Analysis for the same period.
All of the above have been posted on the Company’s website www.rupertresources.com with the financial statements and MD&A also published on SEDAR+ at www.sedarplus.ca
James Withall, Chief Executive Officer of Rupert Resources said “Following the completion of the successful financings over the summer the company remains well funded heading into the winter drilling season and CEO transition with a cash balance of $52M. The PFS for Ikkari continues to progress with critical path items substantially complete. Review and optimisation work will be undertaken in Q4 2024 by the incoming CEO.”
Financial Highlights
During the six months ending August 31, 2024, the Company spent $17,711,186 on its exploration projects. As of August 31, 2024, Rupert held cash or cash equivalents of $52,422,385. The Company recorded a net loss and comprehensive loss for the three and six months to end-August 2024 of $(1,453,606) and $(2,199,432) respectively and a net loss per share of $(0.01) and $(0.02) respectively.
All references to currency in this press release are in Canadian dollars.
During the three and six months ended August 31, 2024 and up to the date of this document, Rupert’s operational activities have been focussed on the Rupert Lapland Project Area and Ikkari in particular.
Rupert Lapland Project Area
Regional Exploration Program, including Ikkari
The regional exploration program at the Rupert Lapland Project Area is designed to identify and evaluate the mineral potential contained in Rupert’s land package in the CLGB.
Since July 2020 the Company has been engaged in a diamond drill program to further evaluate discoveries made within the Rupert Lapland Project Area, including Ikkari, as well as continuing to generate new targets through base of till (“BoT”) sampling, which continues across the Rupert Lapland Project Area and specifically over geophysical anomalies of interest.
The Updated Ikkari MRE has served as the basis for the Pre-feasibility Study (“Ikkari PFS”) that was initiated during the twelve months ended February 29, 2024.
Ikkari Project Drilling
The 2023/24 drill program was completed during the second calendar quarter of 2024, comprising some 43,000 metres (“m”) of drilling, with 24,000m allocated to drilling within the Ikkari project footprint.
During the 2024/25 drill season the focus of Ikkari project drilling will be on ensuring a thorough understanding of the short-spaced grade variability, the hydrogeological environment and geotechnical domains to facilitate the full optimisation of the project at the definitive feasibility study stage which is expected to follow on from successful completion of the Ikkari PFS.
Continuing Exploration
Following on from the success of the exploration campaign during the winter 2023/24, the discovery of significant widths and tenors of mineralisation at Heinä South, and the structural reinterpretation of the wider Area 1, the 2024/25 exploration program is now underway with drilling planned at six target areas along the 15km regional trend east of Ikkari as well as two base metals target areas located at the east of Rupert’s 100% property. The aim of the upcoming season is to systematically explore extensions to the prospective structures identified in an updated structural interpretation.
Engineering and PFS update
In August final metallurgical variability and bulk testwork results were released providing evidence of favourable recoveries using the proposed gravity and whole ore leach flow sheet that will be applied in the upcoming PFS. Other critical path work has been substantially finished and review and optimisation work will be undertaken in calendar Q4 2024.
Advancing Permitting and Environmental Work
As part of this process the Company continues with numerous baseline environmental assessments, as well as on-going engagement across all stakeholder groups. The Ikkari PFS is drawing from these processes as appropriate.