||
Rupert Resources
SUBSCRIBE

Prefeasibility Study (2025)

IKKARI PFS: COMPELLING PROJECT ECONOMICS WITH LEVERAGE TO HIGHER GOLD PRICES

  • Probable Mineral Reserve of 52Mt at 2.1g/t Au for 3.5Moz Au
  • After-tax Net Present Value (5% discount) (“NPV”) of $1.7 billion with unlevered Internal Rate of Return (“IRR”) of 38% and payback after 2.2 years, assuming long term market consensus gold price of $2,150 per troy ounce (“oz”). NPV of $2.5 billion with IRR of 49% and 1.7 year payback at $2,650/oz.
  • Expected lowest quartile all-in sustaining cost (“AISC”) of $918/oz over LOM, and $717/oz during years 1 to 10 primarily due to a high open pit grade and low strip ratio.
  • Long life: 20-year life of mine (“LOM”) comprising an open-pit operation for the first 10 years with average annual production of 227koz per annum, transitioning to an underground operation (years 10 - 20).
  • Manageable initial capital requirement of $575 million including contingency with project maintaining the low capital intensity indicated by the 2022 Preliminary Economic Assessment (“PEA”).
  • 100% Contained within Rupert Property: All project infrastructure contained within Rupert’s 100% owned exploration licences. Access road, power line and discharge pipeline permitted though separate auxiliary permitting process and do not require siting on mining or exploration permits held by Rupert Resources.
  • First gold pour targeted in 2030 based on Environmental Impact Assessment (“EIA”) submission and Definitive Feasibility Study (“DFS”) initiation in H2 2025, a 24-month permitting timeline and a 2½ year construction period.
PFS results highlights

Overview

The Ikkari PFS envisages a staged mine design to minimise waste stripping and enable early production from high grade areas in the open pit. The open pit will produce ore for 10 years before transitioning to a long hole open stope (“LHOS”) underground mine from year 10 for the remainder of the 20-year LOM. Both the grade and the low strip ratio in the open pit are key drivers of a lowest quartile ASIC operation set out in the PFS. An expected lowest quartile all-in sustaining cost (“AISC”) of $759/oz is outlined over LOM, and $717/oz during the first ten years.

HIGHLIGHTS

FINANCIAL HIGHLIGHTS

Life Of Mine Years 20
Net Present Value (5% discount rate) USD Million 1,700
Internal rate of return (unlevered) % 38
Payback Years 2.2
Capital expenditure (Initial) USD million 570
Capital expenditure (Sustaining) USD million 571
Gross revenue USD million 7,200
Operating cost USD million 2,400
Free cash (after tax) USD million 2,800

PRODUCTION HIGHLIGHTS

Years 1 to 10 LOM (20 years)
Milled tonnes Million tonnes 35.0 52.0
Mill throughput Million tonnes per annum 3.5 2.6
Strip ratio Waste : Ore 3.6 3.6
Average processed grade Grams per tonne (gold) 2.1 2.1
Average metallurgical recovery % 95.8 95.8
Average annual gold production 000 troy ounces (k oz) 227 167
Recovered gold Million troy ounces 2.3 3.3
Total Cash Cost $ / troy ounce 603 747
Sustaining Capital $ / troy ounce 115 171
All in Sustaining Cost (AISC) $ / troy ounce 717 918